Download eBook of The Week

Title: Innovation Strategies for a Global Economy Development, Implementation, Measurement and Management
Download Links: Option 1 or Option 2 ----> Read more about this book
| 0 comments ]

You have just determined that your service employees have used a total of 2400 hours of labor this week to process 560 insurance forms. Last week the same crew used only 2000 hours of labor to process 480 forms.

Which productivity measure should be used?

Answer: Could be classified as a Total Measure or Partial Measure.

Is productivity increasing or decreasing?

Answer: Last week’s productivity = 480/2000 = 0.24, and this week’s productivity is = 560/2400 = 0.23. So, productivity is decreasing slightly.



Share/Save/Bookmark

0 comments

Post a Comment

Related Posts with Thumbnails